Section 2 established that California High-Speed Rail is now funded almost entirely from California-only sources, and that the bond authorization carries an operating-subsidy prohibition the segment under construction does not meet on CHSRA's current forecast. This section turns to the spending records themselves.
We analyzed 32 months of CHSRA vendor payments from July 2023 through February 2026, (the most recent CHSRA vendor-payment data available from Open Fi$Cal) to answer: where did the money go, and what did it buy?[12]
Our data warehouse helped us transform raw accounting codes into public-facing explanations with caveats, source documentation and confidence levels to answer questions about deliverables, milestones, and risk.
Net Payments
$3.68B
CHSRA vendor payments in the 32-month window
Window
32 months
July 2023 through February 2026
Concentration
31 payees
About 96% of recent net payments
Construction
$2.14B
About 58% to Construction Package (CP) 1, CP 2-3, and CP 4 primes
Professional Support
$896M
13 firms / joint ventures, 16 active contracts
What Enrichment Added
Layer 1
Payee identity
Vendor names were normalized and classified so contractors, agencies, railroads, utilities, title firms, and confidential right-of-way (ROW) payments were not treated as one generic vendor list.
Layer 2
Contract context
Payment totals were linked to CHSRA contract numbers where public records supported the match, separating civil works from design, program management, rail delivery, and public-agency agreements.
Layer 3
Evidence confidence
Each finding includes a confidence level, so readers can distinguish validated findings from probable matches, unresolved labels, and records requiring California Public Records Act (CPRA) follow-up.
Layer 4
Delivery question
The enriched record moved the question from "who was paid?" to "what did the payment support, and can that support be tied to progress toward revenue service?"
Where The $3.68 Billion Went
Our vendor classification process shows that direct construction is the largest recent spending category, but a large share also supports management, design, coordination, and project infrastructure. The estimates below are cross-referenced against CHSRA contract and expenditure reports where contract numbers are available.[13][14]
Construction packagesConstruction Package (CP) 1, CP 2-3, CP 4 civil works
~$2.136B | 58.1%
Professional services and designProgram management, rail delivery, project controls, engineering
~$975M | 26.5%
Public-agency / railroad / utility coordinationBNSF, Caltrain, LA Metro, Caltrans, PG&E, UPRR
~$417M | 11.4%
ROW and relocation in the 32-month payment windowRecent right-of-way, title, escrow, acquisition support, legal, and confidential rows
~$79M | 2.1%
Environmental, legal, IT, and otherOther smaller vendors and lower-confidence categories
~$68M | 1.9%
Detailed category reconciliation is important because confidence ratings vary by category. Open Fi$Cal shows who was paid and when; contracts and other supporting documents are required to understand what each payment delivered.
| Category |
Representative Payees / Contracts |
Estimated $ |
Share |
Confidence |
Construction packages Construction Package (CP) 1, CP 2-3, CP 4 civil works |
Tutor Perini / Zachry / Parsons (HSR13-06); Dragados / Flatiron (HSR13-57); California Rail Builders (HSR14-32) |
|
58.1% |
High |
| Program management, rail delivery, and project controls |
AECOM-Fluor (HSR21-17); Wong+Harris (HSR11-20); Arcadis (HSR13-81); HNTB (HSR15-01); WSP (HSR14-66); DB E.C.O. North America (HSR17-20) |
|
19.7% |
Medium |
| Public-agency, railroad, and utility coordination |
BNSF; Peninsula Corridor JPB / Caltrain; LA Metro; Caltrans; PG&E; UPRR |
|
11.4% |
Medium |
| Design and engineering |
Stantec; Systra-Typsa; SmithGroup; Arup; STV; Sener; T.Y. Lin International |
|
6.8% |
Medium |
| Right-of-way and relocation in the 32-month payment window |
Title / escrow firms; acquisition-support firms; condemnation / right-of-way legal; Uniform Act confidential bucket |
|
2.1% |
Medium-low |
| Environmental, legal, IT, and other |
Legal counsel, environmental consultants, IT services, leases, materials, unresolved labels, and other smaller vendors |
|
1.9% |
Low-medium |
| Total |
32-month CHSRA Fi$Cal slice |
~$3.676B |
100.0% |
|
Source data is the Open Fi$Cal public payments dataset cross-referenced against CHSRA's F&A Contracts Expenditures Reports and Capital Outlay Budget and Expenditures Reports. Category estimates sum to $3,675,744,000 against the Fi$Cal payee-row total rounded to $3.68 billion, a variance of $4.3 million, or 0.12 percent.
Right-Of-Way Is Not One Story
The 171-mile Merced-to-Bakersfield initial operating segment is not a single uniform construction zone. The 119-mile middle, between Madera and Poplar Avenue, represents about 70 percent of the route and is under active construction with right-of-way substantially complete. The 52 miles of endpoint extensions, connecting Madera north into Merced and Poplar Avenue south into Bakersfield, represent about 30 percent of the route and are still in design, with parcel acquisition only beginning to commence.[15][16]
The hidden ROW risk is at the endpoints: CHSRA has acquired ROW for over 99% of the 119-mile middle segment, but the Merced and Bakersfield extensions must still be acquired, cleared and assembled before the full 171-mile IOS can operate as a rail service.
North endpoint
Merced extension
~34 miles, about 20% of IOS. Design phase; parcel list not yet published and acquisition only beginning to commence. Remaining cost estimate about $2.3B.
ROW appears to involve a smaller number of larger agricultural parcels; potentially fewer separate owners, lower administrative overhead and eminent-domain exposure.
Active construction middle
Madera-Poplar Avenue
119 miles, about 70% of IOS, across CP 1, CP 2-3, and CP 4.
ROW substantially delivered
2,276 of 2,294 parcels, or 99.2%.
Cumulative ROW spend about $1.51B-$1.53B program-to-date.
South endpoint
Bakersfield extension
~18 miles, about 10% of IOS. Design phase; parcel list not yet published and acquisition only beginning to commence. Remaining cost estimate about $1.3B.
ROW appears to involve a larger number of smaller urban parcels; potentially more separate owners, higher administrative overhead and eminent-domain exposure.
Total initial operating segment (IOS)
171 miles: Merced to Bakersfield
119-mile active-construction middle plus approximately 52 miles of endpoint extensions; about 30% of route miles still carry endpoint ROW assembly risk.
A high-speed rail line cannot enter revenue service on a corridor whose endpoints have not been assembled. The 119-mile civil-works completion CHSRA correctly highlights is necessary, but it does not by itself make the 171-mile IOS revenue-service ready for the 2032 / 2033 target.
Construction Packages And Professional Services Dominate
Approximately $2.14 billion, or 58.1 percent of the 32-month total, flowed to the three primary contractors building the 119-mile active-construction zone. These payments fund the physical work: grading, structures, viaducts, grade separations, and embankments along the alignment.
A second large stream flowed to professional-services firms. They fund the machinery that manages the project: program oversight, design review, project controls, operational readiness, station planning, and change-order administration. However, they do not themselves prove physical progress. Of the $3.68 billion paid over 32 months, $896.4 million flowed to thirteen firms and joint ventures holding sixteen active professional-services contracts.[17]
| Firm / JV |
Contract(s) |
Scope |
Paid In Window |
| AECOM-Fluor JV | HSR21-17 | Program delivery support | |
| Wong + Harris JV | HSR11-20 | PCM: CP 1 | |
| Arcadis | HSR13-81 | PCM: CP 2-3 | |
| HNTB | HSR15-01; HSR15-34; HSR22-01 | PCM CP 4; environmental and engineering | |
| Stantec | HSR22-02 | Design services | |
| F+P Arup JV | HSR21-07 | Station planning | |
| Systra-Typsa JV | HSR23-32 | Track and OCS design | |
| DB E.C.O. North America | HSR17-20 | Early Train Operator / operational readiness | |
| Other named firms | Multiple | Preliminary engineering, sustainability, station delivery, and environmental support | |
| Total | | | $896.4M |
These firms act as extended CHSRA technical staff. They also prepare, review, negotiate, and administer amendments and change orders. Dollars spent on project support may be necessary, but they do not themselves construct guideway, track, structures, or systems.
What Fi$Cal Cannot Show Alone
Fi$Cal can show when a vendor was paid and how much. It does not tell what work products were received, whether they were completed on schedule, or whether they advanced a milestone tied to revenue service. It also does not separate original-scope payments from payments made under later amendments or change orders without additional contract records.
Payment Records Show
- Payee name
- Payment timing
- Net amount
- Agency, fund, and account context
- Contract identity where external records allow matching
Payment Records Do Not Show Alone
- Specific deliverable received
- Milestone completion
- Original-scope vs. change-order scope
- Schedule recovery
- Whether the payment advanced revenue service
This is not a criticism of Fi$Cal. The system is doing what it was designed to do. The payment record is necessary, but not sufficient. That is why the next section applies a transparency test: not whether spending occurred, but whether the public can connect spending to deliverables, dates, enforceable terms, and independently verifiable progress.